top of page

Construction diary

Ready set, go!

In 2020 & 2021 there were many changes in and around the house. Due to the Covid-19 situation, the starting signal for the construction of the natural pool was given in March 2021.

We have captured the photos and the construction phases for you.

IMG_20210522_102421.jpg

Start of construction project natural pool

Friday, March 5th, 2021

We have waited a long time for this - the day has finally come.

Excavation

Saturday, March 6th, 2021

The big machines are coming today!

Large base plate & base plate of the regeneration shaft

Wednesday, March 10th, 2021 & Thursday, March 11th, 2021

The large floor slab was completed on Wednesday and the floor for the regeneration shaft was concreted on Thursday!

Small base plate & walls

Saturday, March 13th, 2021 & Monday, March 15th, 2021

Preparations for concreting the small floor slab and the first walls. The concrete delivery came the following Monday.

Completion of concrete work & insulation

Friday, March 26th, 2021 to Tuesday, March 30th, 2021

We sometimes had to put in "weather shifts" on certain days because the weather didn't quite play along with us. But now it's done and the pool linen can come!

The pool liner is coming!

Thursday, April 8th, 2021 & Friday, April 9th, 2021

It's hard to believe, it has only been a month since construction began, but in a few days we can fill our natural pool with water for the first time!

The liner is done!

Monday April 12th, 2021 to Thursday April 15th, 2021

The foil in the swimming area was completely laid, then water was let into the pool for the first time so that no holes would appear if any objects fell into. The majority around the swimming area has already been filled with soil for the regeneration zone.

Foundations for the stone walls

Friday April 23rd, 2021 to Tuesday April 27th, 2021

Between the Hotel and the Gänsleit street as well as around the pool comes a concrete base for the stone walls.

Preparation of the filter & regeneration zone

Wednesday May 5th, 2021 to Monday May 10th 2021

The pool liner in the regeneration zone and in the filter shaft was placed and filled with stones/gravel. Our pool robot has made its first rounds in the pool.

Planting regeneration & start of paving work

Tuesday, May 18th, 2021 to Friday, May 28th, 2021

The regeneration zone was filled with substrate and water. Work on the paving began the following week.

Tree regeneration & completion terrace

Wednesday June 2nd, 2021

The large tree behind the regeneration area was delivered and planted.. The paving work has been completed.

Trees terrace & wall street side

Friday June 4th, 2021

The 3 new trees in the guest garden were planted and the stone wall was set.

bottom of page