Construction diary
Ready set, go!
In 2020 & 2021 there were many changes in and around the house. Due to the Covid-19 situation, the starting signal for the construction of the natural pool was given in March 2021.
We have captured the photos and the construction phases for you.
Start of construction project natural pool
Friday, March 5th, 2021
We have waited a long time for this - the day has finally come.
Excavation
Saturday, March 6th, 2021
The big machines are coming today!
Large base plate & base plate of the regeneration shaft
Wednesday, March 10th, 2021 & Thursday, March 11th, 2021
The large floor slab was completed on Wednesday and the floor for the regeneration shaft was concreted on Thursday!
Small base plate & walls
Saturday, March 13th, 2021 & Monday, March 15th, 2021
Preparations for concreting the small floor slab and the first walls. The concrete delivery came the following Monday.